BEMIDJI,
Minn. – Motorists on Highway 75 and 200 in northwestern Minnesota will
experience lane closures and periodic delays beginning Monday, May 11,
as crews begin work. Highway 75 will see resurfacing work from CSAH 19
just north of Halstad, to Mauritson Avenue in Shelly. Highway 200 will
be resurfaced from the North Dakota border to 240th Avenue in Halstad.
Other components of the project will include culvert replacements, as well as storm sewer and ADA improvements in Shelly.
A
one-week detour along Highway 75 one-half mile north of Halstad will go
into effect May 18. Traffic will be detoured east one-half mile on CSAH
19, south one-half mile on CSAH 51, and then west one-half mile on
CSAH 51 back to Highway 75.
The project is expected to conclude in mid-June, weather permitting.
For statewide travel information, visit www.511mn.org.